Sturgeon Point pool rebuild project can be viewed in the picture slider below. The pool reopened the weekend of 6/20/2020.
- 11/30/2019 Pool removal
- 11/30/2019 Pool removal
- 11/30/2019 Pool removal
- 5/4/2020 Start pool installation
- 5/5/2020
- 5/6/2020
- 5/7/2020
- 5/8/2020
- 5/11/2020
- 5/12/2020
- 5/13/2020
- 5/14/2020
- 5/14/2020
- 5/14/2020
- 5/14/2020
- 5/19/2020 Plumbing and wiring
- 5/20/2020 Plumbing work
- 5/21/2020 Pool walls backfilled
- 5/22/2020 Poured some of the bottom
- 5/22/2020
- 5/23/2020
- 5/26/2020
- 5/27/2020 Steps added
- 5/30/2020
- 6/1/2020
- 6/3/2020
- 6/3/2020
- 6/4/2020 First coat of paint
- 6/5/2020 Second coat of paint
- 6/11/2020 Filling with water
- 6/12/2020
- 6/21/2020 It's open!
- 8/25/2020 Install pool cover